Which of the following activities is necessary for the capacity availability check that can be carried out automatically when a production order is released?

The correct answer is B. Activate the availability check and assign an overall profile in the checking control of the order type / plant. See the full explanation below for the reasoning.

Question

Which of the following activities is necessary for the capacity availability check that can be carried out automatically when a production order is released?

Options

  • ASet the finite scheduling indicator and assign a checking rule in the work center for the operation to be
  • BActivate the availability check and assign an overall profile in the checking control of the order type / plant
  • CAssign an appropriate availability checking rule to the material master for the product.
  • DActivate the availability check and assign an overall profile in the production scheduling profile.

How the community answered

(35 responses)
  • A
    9% (3)
  • B
    71% (25)
  • C
    3% (1)
  • D
    17% (6)