C_TSCM42_66 · Question #37
Which of the following activities is necessary for the capacity availability check that can be carried out automatically when a production order is released?
The correct answer is B. Activate the availability check and assign an overall profile in the checking control of the order type / plant. See the full explanation below for the reasoning.
Question
Which of the following activities is necessary for the capacity availability check that can be carried out automatically when a production order is released?
Options
- ASet the finite scheduling indicator and assign a checking rule in the work center for the operation to be
- BActivate the availability check and assign an overall profile in the checking control of the order type / plant
- CAssign an appropriate availability checking rule to the material master for the product.
- DActivate the availability check and assign an overall profile in the production scheduling profile.
How the community answered
(35 responses)- A9% (3)
- B71% (25)
- C3% (1)
- D17% (6)