C_TSCM42_66 · Question #33
You have maintained planning strategy group 10 (make-to-stock production) in the material master (SAP ECC) of a material. For the coming months, you have planned requirements with requirement type…
The correct answer is A. You can enter the strategy group 40 in the material master, but the requirement type is not changed D. You can enter the strategy group 40 in the material master and change the present requirement for the. See the full explanation below for the reasoning.
Question
You have maintained planning strategy group 10 (make-to-stock production) in the material master (SAP ECC) of a material. For the coming months, you have planned requirements with requirement type LSF (derived from main strategy 10). Now, you want to change the requirement type from LSF to VSF (in accordance with planning strategy 40, planning with final assembly) for requirements in the existing production plan. Which of the following scenarios are applicable in this case? (Choose two)
Options
- AYou can enter the strategy group 40 in the material master, but the requirement type is not changed
- BYou must change the requirement type for planning strategy 10 to VSF in Customizing. The requirement
- CYou can change the strategy group from 10 to 40 for the existing production plan in the material master,
- DYou can enter the strategy group 40 in the material master and change the present requirement for the
How the community answered
(28 responses)- A82% (23)
- B7% (2)
- C11% (3)