C_TSCM42_66 · Question #3

You want to plan a finished material using material requirements planning in an SAP ECC system. The resulting planned orders should be scheduled using basic date scheduling (not lead- time…

The correct answer is D. In multi-level backward scheduling, dependent requirements are triggered at the start date for the planned. See the full explanation below for the reasoning.

Question

You want to plan a finished material using material requirements planning in an SAP ECC system. The resulting planned orders should be scheduled using basic date scheduling (not lead- time scheduling). Which of the following properties for the resulting dependent requirements applies?

Options

  • AIn multi-level backward scheduling, dependent requirements are calculated to the exact second.
  • BIf the individual material components are explicitly assigned to the operations of a routing, the requirement
  • CWhen a customer order is created for the finished material, the dependent requirements are automatically
  • DIn multi-level backward scheduling, dependent requirements are triggered at the start date for the planned

How the community answered

(32 responses)
  • A
    13% (4)
  • B
    3% (1)
  • C
    9% (3)
  • D
    75% (24)