You want to plan a finished material using material requirements planning in an SAP ECC system. The resulting planned orders should be scheduled using basic date scheduling (not lead- time…
The correct answer is D. In multi-level backward scheduling, dependent requirements are triggered at the start date for the planned. See the full explanation below for the reasoning.
Question
You want to plan a finished material using material requirements planning in an SAP ECC system. The resulting planned orders should be scheduled using basic date scheduling (not lead- time scheduling). Which of the following properties for the resulting dependent requirements applies?
Options
- AIn multi-level backward scheduling, dependent requirements are calculated to the exact second.
- BIf the individual material components are explicitly assigned to the operations of a routing, the requirement
- CWhen a customer order is created for the finished material, the dependent requirements are automatically
- DIn multi-level backward scheduling, dependent requirements are triggered at the start date for the planned
How the community answered
(32 responses)- A13% (4)
- B3% (1)
- C9% (3)
- D75% (24)