C_TSCM42_66 · Question #3

C_TSCM42_66 Question #3: Real Exam Question with Answer & Explanation

Sign in or unlock C_TSCM42_66 to reveal the answer and full explanation for question #3. The question stem and answer options stay visible for context.

Question

You want to plan a finished material using material requirements planning in an SAP ECC system. The resulting planned orders should be scheduled using basic date scheduling (not lead- time scheduling). Which of the following properties for the resulting dependent requirements applies?

Options

  • AIn multi-level backward scheduling, dependent requirements are calculated to the exact second.
  • BIf the individual material components are explicitly assigned to the operations of a routing, the requirement
  • CWhen a customer order is created for the finished material, the dependent requirements are automatically
  • DIn multi-level backward scheduling, dependent requirements are triggered at the start date for the planned