In which master data object do you set the standard values for an operation?

The correct answer is C. Routing. See the full explanation below for the reasoning.

Question

In which master data object do you set the standard values for an operation?

Options

  • AMaterial Master
  • BWork Center
  • CRouting
  • DProduction Resource/Tool (PRT)

How the community answered

(47 responses)
  • A
    11% (5)
  • B
    4% (2)
  • C
    79% (37)
  • D
    6% (3)