How can you configure cycles for period-end allocation? There are TWO correct answers for this question
The correct answer is C. Define allocation for the same cost center in multiple segments D. Assign several segments to a cycle. See the full explanation below for the reasoning.
Question
How can you configure cycles for period-end allocation? There are TWO correct answers for this question
Options
- ACreate cycles that iterate with each other
- BUse different allocation rules within one segment
- CDefine allocation for the same cost center in multiple segments
- DAssign several segments to a cycle
How the community answered
(33 responses)- A6% (2)
- B15% (5)
- C79% (26)
Community Discussion