How can you configure cycles for period-end allocation? There are TWO correct answers for this question

The correct answer is C. Define allocation for the same cost center in multiple segments D. Assign several segments to a cycle. See the full explanation below for the reasoning.

Question

How can you configure cycles for period-end allocation? There are TWO correct answers for this question

Options

  • ACreate cycles that iterate with each other
  • BUse different allocation rules within one segment
  • CDefine allocation for the same cost center in multiple segments
  • DAssign several segments to a cycle

How the community answered

(33 responses)
  • A
    6% (2)
  • B
    15% (5)
  • C
    79% (26)