Which activities can you perform while you create cost center hierarchies? There are 2 correct answers to this question

The correct answer is A. Reassign a cost center to another node of the standard hierarchy. D. Append nodes and cost centers to a node of the standard hierarchy. See the full explanation below for the reasoning.

Question

Which activities can you perform while you create cost center hierarchies? There are 2 correct answers to this question

Options

  • AReassign a cost center to another node of the standard hierarchy.
  • BAssign a standard hierarchy to several controlling areas.
  • CCreate a cost center without specifying a standard hierarchy
  • DAppend nodes and cost centers to a node of the standard hierarchy.

How the community answered

(26 responses)
  • A
    81% (21)
  • B
    12% (3)
  • C
    8% (2)