Which activities can you perform while you create cost center hierarchies? There are 2 correct answers to this question
The correct answer is A. Reassign a cost center to another node of the standard hierarchy. D. Append nodes and cost centers to a node of the standard hierarchy. See the full explanation below for the reasoning.
Question
Which activities can you perform while you create cost center hierarchies? There are 2 correct answers to this question
Options
- AReassign a cost center to another node of the standard hierarchy.
- BAssign a standard hierarchy to several controlling areas.
- CCreate a cost center without specifying a standard hierarchy
- DAppend nodes and cost centers to a node of the standard hierarchy.
How the community answered
(26 responses)- A81% (21)
- B12% (3)
- C8% (2)