C_TS4CO_1909 · Question #71

How does the system derive the requirement type from the material master data ?

The correct answer is A. MRP group -> strategy group -> planning strategy -> requirements type B. Strategy group -> planning strategy -> requirements type. See the full explanation below for the reasoning.

Question

How does the system derive the requirement type from the material master data ?

Options

  • AMRP group -> strategy group -> planning strategy -> requirements type
  • BStrategy group -> planning strategy -> requirements type
  • CMRP group requirements class -> planning strategy -> requirements type
  • DStrategy group -> planning strategy -> requirements class -> requirements type

How the community answered

(44 responses)
  • A
    73% (32)
  • C
    9% (4)
  • D
    18% (8)

Community Discussion

No community discussion yet for this question.