SAP
C_TS4CO_1909 · Question #71
How does the system derive the requirement type from the material master data ?
The correct answer is A. MRP group -> strategy group -> planning strategy -> requirements type B. Strategy group -> planning strategy -> requirements type. See the full explanation below for the reasoning.
Question
How does the system derive the requirement type from the material master data ?
Options
- AMRP group -> strategy group -> planning strategy -> requirements type
- BStrategy group -> planning strategy -> requirements type
- CMRP group requirements class -> planning strategy -> requirements type
- DStrategy group -> planning strategy -> requirements class -> requirements type
How the community answered
(44 responses)- A73% (32)
- C9% (4)
- D18% (8)
Community Discussion
No community discussion yet for this question.