SAP
C_TS4CO_1909 · Question #59
You want to run an assessment cycle in Profitability Analysis to allocate cost centers costs during period-end closing for your organization. Which of the following objects is part of the assessment…
The correct answer is D. Tracing factor. See the full explanation below for the reasoning.
Question
You want to run an assessment cycle in Profitability Analysis to allocate cost centers costs during period-end closing for your organization. Which of the following objects is part of the assessment cycle?
Options
- ACycle iteration
- BPA transfer structure
- CTemplate
- DTracing factor
How the community answered
(63 responses)- A2% (1)
- B6% (4)
- C11% (7)
- D81% (51)
Community Discussion