C_TS4CO_1909 · Question #48

You have activated budget availability control for an internal order and entered an overall budget of 10000. Actuals of 10000 were posted for this internal order in the current year. How is that…

The correct answer is A. The purchase order was entered in a different year than the budget C. The cost element is exempted from budget availability control. See the full explanation below for the reasoning.

Question

You have activated budget availability control for an internal order and entered an overall budget of 10000. Actuals of 10000 were posted for this internal order in the current year. How is that possible ? 2 Answer

Options

  • AThe purchase order was entered in a different year than the budget
  • BThe purchase order has NOT generated a budget document yet.
  • CThe cost element is exempted from budget availability control
  • DThe difference of 1000 is within the tolerance limits defined in the configuration

How the community answered

(19 responses)
  • A
    79% (15)
  • B
    16% (3)
  • D
    5% (1)

Community Discussion

No community discussion yet for this question.