What can you use to difference two or more cost estimates fo rthe same material ? 2 answers

The correct answer is C. Costing variant D. Costing version. See the full explanation below for the reasoning.

Question

What can you use to difference two or more cost estimates fo rthe same material ? 2 answers

Options

  • AValuation variant
  • BTransfer control
  • CCosting variant
  • DCosting version