C_TS4CO_1909 · Question #37
you are configuring internal order settlement. Where do you define which cost elements should be settled, using either the original or settlement cost elements?
The correct answer is D. Allocation structure. See the full explanation below for the reasoning.
Question
you are configuring internal order settlement. Where do you define which cost elements should be settled, using either the original or settlement cost elements?
Options
- ASettlement profile
- BTemplate
- CSettlement rule
- DAllocation structure
How the community answered
(24 responses)- A4% (1)
- B8% (2)
- C4% (1)
- D83% (20)