C_TS4CO_1909 · Question #32

You want to set up budget availability control for your projects and internal ordders. What can you check using budget availability control? 2 Answers

The correct answer is A. The availability of funds in object currency D. The availability of funds according to tolerance limits. See the full explanation below for the reasoning.

Question

You want to set up budget availability control for your projects and internal ordders. What can you check using budget availability control? 2 Answers

Options

  • AThe availability of funds in object currency
  • BThe availability of funds using overall plan value
  • CThe availability of funds on period level
  • DThe availability of funds according to tolerance limits

How the community answered

(54 responses)
  • A
    74% (40)
  • B
    19% (10)
  • C
    7% (4)