Which of the following objects can be selected in templates for activity-based costing? 2 answers

The correct answer is B. Cost center/activity typ C. Business process. See the full explanation below for the reasoning.

Question

Which of the following objects can be selected in templates for activity-based costing? 2 answers

Options

  • AWBS element
  • BCost center/activity typ
  • CBusiness process
  • Dinternal order

How the community answered

(26 responses)
  • A
    8% (2)
  • B
    77% (20)
  • D
    15% (4)