What is required before you can create a multi-level material cost estimate without quantity structure?
The correct answer is A. Material master with costing view. See the full explanation below for the reasoning.
Question
What is required before you can create a multi-level material cost estimate without quantity structure?
Options
- AMaterial master with costing view
- BSpecific valuation variants for material costings without quantity structure
- CMaterial master with accounting view and with MRP views
- DSpecific costing variants for material costings without quantity structure
How the community answered
(40 responses)- A85% (34)
- B3% (1)
- C5% (2)
- D8% (3)