C_TS4CO_1909 · Question #19

Plan revenue = 3000 Plan costs = 2000 Actual revenue = 1200 Actual costs = 1000

The correct answer is D. Revenue 1500; Cost of sales = 1000; Capitalized revenue (revenue in excess of billing) = 200. See the full explanation below for the reasoning.

Question

Plan revenue = 3000 Plan costs = 2000 Actual revenue = 1200 Actual costs = 1000

Options

  • ARevenue 1500; Cost of sales = 1000; Capitalized revenue (revenue in excess of billing) = 300
  • BRevenue 1500; Cost of sales = 1000; Revenue surplus = 200
  • CRevenue 1500; Cost of sales = 1000; Revenue surplus = 300
  • DRevenue 1500; Cost of sales = 1000; Capitalized revenue (revenue in excess of billing) = 200

How the community answered

(32 responses)
  • A
    3% (1)
  • B
    16% (5)
  • C
    6% (2)
  • D
    75% (24)