You want to creat cost centers for you company. What is the prerequisite to building an organizational structure for overhead cost controlling?
The correct answer is C. Standard hierarchy top node. See the full explanation below for the reasoning.
Question
You want to creat cost centers for you company. What is the prerequisite to building an organizational structure for overhead cost controlling?
Options
- ACost center category
- BCost center type
- CStandard hierarchy top node
- DFunctional area
How the community answered
(17 responses)- A6% (1)
- B6% (1)
- C76% (13)
- D12% (2)