What do you do to create a primary cost component split? There are TWO correct answers for this question
The correct answer is A. Assign a cost component structure to the CO-version C. Run an activity price calculation. See the full explanation below for the reasoning.
Question
What do you do to create a primary cost component split? There are TWO correct answers for this question
Options
- AAssign a cost component structure to the CO-version
- BUse the cost splitting tool on cost centers
- CRun an activity price calculation
- DEnter split activity prices manually
How the community answered
(47 responses)- A72% (34)
- B19% (9)
- D9% (4)