You want to create a new standard cost estimate based on the quantity structure of the existing standard cost estimate. Which object do you use ?
The correct answer is A. Costing type. See the full explanation below for the reasoning.
Question
You want to create a new standard cost estimate based on the quantity structure of the existing standard cost estimate. Which object do you use ?
Options
- ACosting type
- BTransfer control
- CReference variance
- DCosting version
How the community answered
(24 responses)- A83% (20)
- B4% (1)
- C13% (3)