Which cost estimates must you reuse with the transfer control functionality?

The correct answer is B. Cost estimates with same cost component structure. See the full explanation below for the reasoning.

Question

Which cost estimates must you reuse with the transfer control functionality?

Options

  • ACost estimates across company codes
  • BCost estimates with same cost component structure
  • CCost estimates with quantity structure
  • DCost estimates within the same plant

How the community answered

(27 responses)
  • A
    4% (1)
  • B
    81% (22)
  • C
    11% (3)
  • D
    4% (1)