SAP
C_TS4CO_1909 · Question #168
Which cost estimates must you reuse with the transfer control functionality?
The correct answer is B. Cost estimates with same cost component structure. See the full explanation below for the reasoning.
Question
Which cost estimates must you reuse with the transfer control functionality?
Options
- ACost estimates across company codes
- BCost estimates with same cost component structure
- CCost estimates with quantity structure
- DCost estimates within the same plant
How the community answered
(27 responses)- A4% (1)
- B81% (22)
- C11% (3)
- D4% (1)
Community Discussion
No community discussion yet for this question.