C_TS4CO_1909 Question #148: Real Exam Question with Answer & Explanation

The correct answer is B. It is a structure to which all the cost centers within a controlling area are assigned. See the full explanation below for the reasoning.

Question

Which statement best describes a cost center standard hierarchy?

Options

  • AIt is grouped together with alternative hierarchies to represent decision control and repsonsability
  • BIt is a structure to which all the cost centers within a controlling area are assigned
  • CIt represents an organization unit in SAP S/4HANA where the costs and revenues are incurred and
  • DIt enables you to assign the same attributes to similar cost centers within a controlling area

Community Discussion

No community discussion yet for this question.

Full C_TS4CO_1909 Practice
Which statement best describes a cost center standard hierarchy? | C_TS4CO_1909 Q#148 Answer | NerdExam