C_TS4CO_1909 · Question #142

In a make-to-order scenario, you use a sales order with an assigned production order and non- valuated sales order stock. Which process do you use to post actual costs on a sales order in SAP…

The correct answer is B. Production order confirmation C. Production order settlement. See the full explanation below for the reasoning.

Question

In a make-to-order scenario, you use a sales order with an assigned production order and non- valuated sales order stock. Which process do you use to post actual costs on a sales order in SAP S/4HANA? There are TWO correct answers for this question

Options

  • ADelivery from production order to sales order stock
  • BProduction order confirmation
  • CProduction order settlement
  • DExternal goods receipt on sales order stock

How the community answered

(39 responses)
  • A
    18% (7)
  • B
    74% (29)
  • D
    8% (3)

Community Discussion

No community discussion yet for this question.