Which object do you have to assign the cost component structure to?

The correct answer is B. Costing variant. See the full explanation below for the reasoning.

Question

Which object do you have to assign the cost component structure to?

Options

  • ACosting type
  • BCosting variant
  • CValuation variant
  • DMaterial master record

How the community answered

(38 responses)
  • A
    3% (1)
  • B
    79% (30)
  • C
    11% (4)
  • D
    8% (3)