nerdexam
SAP

C_TS4CO_1909 · Question #124

What does the calculation of a condition type in the costing sheet depend on? There are 2 correct answers to this question.

The correct answer is A. Condition class C. Calculation type. See the full explanation below for the reasoning.

Question

What does the calculation of a condition type in the costing sheet depend on? There are 2 correct answers to this question.

Options

  • ACondition class
  • BSegment
  • CCalculation type
  • DValuation

How the community answered

(26 responses)
  • A
    77% (20)
  • B
    15% (4)
  • D
    8% (2)

Community Discussion

No community discussion yet for this question.

Full C_TS4CO_1909 Practice