SAP
C_TS4CO_1909 · Question #124
What does the calculation of a condition type in the costing sheet depend on? There are 2 correct answers to this question.
The correct answer is A. Condition class C. Calculation type. See the full explanation below for the reasoning.
Question
What does the calculation of a condition type in the costing sheet depend on? There are 2 correct answers to this question.
Options
- ACondition class
- BSegment
- CCalculation type
- DValuation
How the community answered
(26 responses)- A77% (20)
- B15% (4)
- D8% (2)
Community Discussion