Question

In the material master record there are three planned prices. What do you use them for? 1 Answer

Options

  • ATo valuate goods movement
  • BTo valuate the materials in cost estimates
  • CTo valuate material stocks
  • DTo update the standard price during the release of a standard cost estimate