In the material master record there are three planned prices. What do you use them for? 1 Answer
The correct answer is D. To update the standard price during the release of a standard cost estimate. See the full explanation below for the reasoning.
Question
In the material master record there are three planned prices. What do you use them for? 1 Answer
Options
- ATo valuate goods movement
- BTo valuate the materials in cost estimates
- CTo valuate material stocks
- DTo update the standard price during the release of a standard cost estimate
How the community answered
(30 responses)- A13% (4)
- B7% (2)
- C3% (1)
- D77% (23)