Which cost objects can only be controlled by period? There are TWO correct answers for this question

The correct answer is B. Cost object hierarchy C. Product cost collector. See the full explanation below for the reasoning.

Question

Which cost objects can only be controlled by period? There are TWO correct answers for this question

Options

  • AProcess order
  • BCost object hierarchy
  • CProduct cost collector
  • DProduction order

How the community answered

(42 responses)
  • A
    10% (4)
  • B
    79% (33)
  • D
    12% (5)