C_TS4CO_1909 · Question #102
Which object can you configure to offset overhead surcharges for a cost object? There are THREE correct answers for this question
The correct answer is B. Business process C. Internal order E. Cost center. See the full explanation below for the reasoning.
Question
Which object can you configure to offset overhead surcharges for a cost object? There are THREE correct answers for this question
Options
- AProfitability segment
- BBusiness process
- CInternal order
- DProfit center
- ECost center
How the community answered
(39 responses)- A18% (7)
- B72% (28)
- D10% (4)