SAP
C_TS460_2021 · Question #24
When creating a sales document with reference, you want the system to automatically copy schedule lines from the source sales document into the target sales document. Where in Customizing would you…
The correct answer is A. In copy control at item level. See the full explanation below for the reasoning.
Question
When creating a sales document with reference, you want the system to automatically copy schedule lines from the source sales document into the target sales document. Where in Customizing would you activate this?
Options
- AIn copy control at item level
- BIn the item category
- CIn the schedule line category
- DIn copy control at schedule line level
How the community answered
(35 responses)- A83% (29)
- B6% (2)
- C3% (1)
- D9% (3)
Community Discussion