SAP
C_TS460_2021 · Question #80
Sales order scheduling uses several lead times. What are the source objects for these lead times? Note: There are 2 correct answers to this question.
The correct answer is B. Route C. Shipping point. See the full explanation below for the reasoning.
Question
Sales order scheduling uses several lead times. What are the source objects for these lead times? Note: There are 2 correct answers to this question.
Options
- ASold-to party
- BRoute
- CShipping point
- DPlant
How the community answered
(36 responses)- A8% (3)
- B75% (27)
- D17% (6)
Community Discussion
No community discussion yet for this question.