You want to use automatic conversion of purchase requisitions into purchase orders for some raw materials. What are the prerequisites? Note: There are 3 correct answers to this question.
The correct answer is B. The Automatic Purchase Order indicator is set in the plant-specific purchasing data of the material C. The Automatic Purchase Order indicator is set in the purchasing data of the business partner D. A source of supply containing valid conditions is assigned to the purchase requisition. Automatic PR-to-PO conversion in SAP MM requires agreement from both master data sides and a ready-to-use source: the material master must have the Automatic PO indicator set in its plant-specific purchasing data (B), the vendor/business partner must also have the Automatic PO…
Question
You want to use automatic conversion of purchase requisitions into purchase orders for some raw materials. What are the prerequisites? Note: There are 3 correct answers to this question.
Options
- AA contract with plant-specific conditions exists for the material and the vendor.
- BThe Automatic Purchase Order indicator is set in the plant-specific purchasing data of the material
- CThe Automatic Purchase Order indicator is set in the purchasing data of the business partner
- DA source of supply containing valid conditions is assigned to the purchase requisition.
- EA plant-specific source list entry exists for the material.
How the community answered
(63 responses)- A6% (4)
- B79% (50)
- E14% (9)
Explanation
Automatic PR-to-PO conversion in SAP MM requires agreement from both master data sides and a ready-to-use source: the material master must have the Automatic PO indicator set in its plant-specific purchasing data (B), the vendor/business partner must also have the Automatic PO indicator set in their purchasing data (C), and the purchase requisition itself must already have a source of supply with valid conditions assigned (D) - without all three, the background job cannot generate a PO without human intervention.
Why A is wrong: Merely having a contract with plant-specific conditions doesn't satisfy the prerequisite on its own; what matters is that a source of supply (which could be that contract) is explicitly assigned to the PR - that's covered by D, not A independently.
Why E is wrong: A source list entry aids source determination, but its existence alone is not a prerequisite for automatic conversion; the source must already be assigned to the requisition (D), not just listed in a source list.
Memory tip: Use the "2 flags + 1 fact" rule - you need 2 flags flipped (on the material AND the vendor) plus 1 fact on the PR (a source with valid conditions already assigned). If any of the three is missing, the automation breaks.