Which of the following procurement proposals can be created during an MRP Live planning run for externally procured materials? Note: There are 2 correct answers to this question.
The correct answer is C. Delivery schedule line D. Purchase requisition. See the full explanation below for the reasoning.
Question
Which of the following procurement proposals can be created during an MRP Live planning run for externally procured materials? Note: There are 2 correct answers to this question.
Options
- APlanned order
- BPurchase order
- CDelivery schedule line
- DPurchase requisition
How the community answered
(71 responses)- A10% (7)
- B20% (14)
- C70% (50)