What are the prerequisites for carrying out material requirements planning (MRP) for a plant? Note: There are 2 correct answers to this question.
The correct answer is B. Maintain plant parameters for the corresponding plant in Customizing. D. Maintain MRP data in the material master record for the materials to be planned automatically. See the full explanation below for the reasoning.
Question
What are the prerequisites for carrying out material requirements planning (MRP) for a plant? Note:
There are 2 correct answers to this question.
Options
- AAssign each storage location of the corresponding plant to an MRP area in Customizing.
- BMaintain plant parameters for the corresponding plant in Customizing.
- CMaintain planned independent requirements for the materials in the plant.
- DMaintain MRP data in the material master record for the materials to be planned automatically.
How the community answered
(32 responses)- A6% (2)
- B81% (26)
- C13% (4)
Community Discussion
No community discussion yet for this question.