Your purchasing organization intends to procure a finished product from a vendor. The vendor will manufacture the product using components provided by your company. Which procurement process do you…

The correct answer is D. Subcontracting. See the full explanation below for the reasoning.

Question

Your purchasing organization intends to procure a finished product from a vendor. The vendor will manufacture the product using components provided by your company. Which procurement process do you use for this scenario? Please choose the correct answer.

Options

  • AStandard
  • BVendor consignment
  • CThird-party
  • DSubcontracting

How the community answered

(48 responses)
  • A
    8% (4)
  • B
    17% (8)
  • C
    4% (2)
  • D
    71% (34)