How does MRP Live minimize the volume of data that must be copied from the database server to the application server and back? Please choose the correct answer. Response:

The correct answer is C. By reading all data in one database procedure. See the full explanation below for the reasoning.

Question

How does MRP Live minimize the volume of data that must be copied from the database server to the application server and back? Please choose the correct answer. Response:

Options

  • ABy reading only the material receipts and requirements
  • BBy reading only the existing purchase requisitions and planned orders
  • CBy reading all data in one database procedure
  • DBy reading only the purchase receipts and requirements

How the community answered

(54 responses)
  • A
    6% (3)
  • B
    4% (2)
  • C
    81% (44)
  • D
    9% (5)