SAP
C_TS452_1909 · Question #45
Which release strategy control prevents a planning run from changing the quantity on a purchase requisition in SAP Materials Management? Please choose the correct answer. Response:
The correct answer is B. Field selection key. See the full explanation below for the reasoning.
Question
Which release strategy control prevents a planning run from changing the quantity on a purchase requisition in SAP Materials Management? Please choose the correct answer. Response:
Options
- AFixing indicator
- BField selection key
- CRelease group
- DRelease code
How the community answered
(24 responses)- A17% (4)
- B71% (17)
- C8% (2)
- D4% (1)
Community Discussion
No community discussion yet for this question.