Which time fields are used during forward scheduling in material requirements planning? There are 2 correct answers to this question.
The correct answer is C. Goods Receipt Processing Time D. Processing Time for Purchasing. See the full explanation below for the reasoning.
Question
Which time fields are used during forward scheduling in material requirements planning? There are 2 correct answers to this question.
Options
- AScheduling Margin Key
- BTotal Replenishment Lead Time
- CGoods Receipt Processing Time
- DProcessing Time for Purchasing
How the community answered
(44 responses)- A18% (8)
- B7% (3)
- C75% (33)
Community Discussion