C_TS410_2504 · Question #73

What is created when you post a valuated goods receipt for consumable materials?

The correct answer is C. Controlling document. When a valuated goods receipt for consumable materials is posted in SAP S/4HANA, a controlling document (C) is created. This document records the financial transaction related to the consumption of materials, impacting cost centers or other relevant controlling objects. The…

Management Accounting

Question

What is created when you post a valuated goods receipt for consumable materials?

Options

  • AMaterial ledger document
  • BVendor invoice document
  • CControlling document
  • DCommitment

How the community answered

(31 responses)
  • A
    10% (3)
  • B
    3% (1)
  • C
    84% (26)
  • D
    3% (1)

Explanation

When a valuated goods receipt for consumable materials is posted in SAP S/4HANA, a controlling document (C) is created. This document records the financial transaction related to the consumption of materials, impacting cost centers or other relevant controlling objects. The controlling document ensures that the costs associated with the consumed materials are accurately reflected in the company's cost accounting and controlling modules.

Topics

#goods receipt#consumable materials#controlling document#cost posting