For which object do you plan activity prices?

The correct answer is A. Cost center. In SAP S/4HANA, activity prices are planned for cost centers (A). Cost centers are organizational units within a company that are responsible for specific areas of cost. Planning activity prices for cost centers involves determining the cost per activity unit for various…

Management Accounting

Question

For which object do you plan activity prices?

Options

  • ACost center
  • BWork center
  • CWBS element
  • DInternal order

How the community answered

(19 responses)
  • A
    89% (17)
  • B
    5% (1)
  • D
    5% (1)

Explanation

In SAP S/4HANA, activity prices are planned for cost centers (A). Cost centers are organizational units within a company that are responsible for specific areas of cost. Planning activity prices for cost centers involves determining the cost per activity unit for various activities performed within the cost center. This is crucial for internal cost allocations, budgeting, and controlling processes.