C_TS410_2504 · Question #37

What is the result of converting a planned order? Note: There are 2 correct answers to this question

The correct answer is B. A purchase requisition D. A production order. Converting a planned order can result in the creation of a Purchase Requisition (B) for externally procured materials or a Production Order (D) for in-house manufactured items. This step is crucial in the procurement and production planning process, initiating the procurement…

Manufacturing

Question

What is the result of converting a planned order? Note: There are 2 correct answers to this question

Options

  • AA planned independent requirement
  • BA purchase requisition
  • CA purchase order
  • DA production order

How the community answered

(71 responses)
  • A
    4% (3)
  • B
    87% (62)
  • C
    8% (6)

Explanation

Converting a planned order can result in the creation of a Purchase Requisition (B) for externally procured materials or a Production Order (D) for in-house manufactured items. This step is crucial in the procurement and production planning process, initiating the procurement or manufacturing of required materials.

Topics

#planned order conversion#production order#purchase requisition#MRP output