SAP
C_TS410_2504 · Question #29
What demand elements are evaluated during a MRP run?
The correct answer is A. Sales orders. During a Material Requirements Planning (MRP) run, Sales Orders (A) are evaluated as demand elements. MRP considers sales orders to determine the required materials and quantities needed to meet customer demand, generating planned orders and purchase requisitions to cover the…
Manufacturing
Question
What demand elements are evaluated during a MRP run?
Options
- ASales orders
- BPlanned orders
- CScheduled lines
- DPurchase requisitions
How the community answered
(39 responses)- A87% (34)
- B3% (1)
- C5% (2)
- D5% (2)
Explanation
During a Material Requirements Planning (MRP) run, Sales Orders (A) are evaluated as demand elements. MRP considers sales orders to determine the required materials and quantities needed to meet customer demand, generating planned orders and purchase requisitions to cover the anticipated demand.
Topics
#MRP demand elements#sales orders#material requirements planning#planning run
Community Discussion