C_TS410_2504 · Question #16

When running MRP, what setting in the material master determines if a material will be procured or produced?

The correct answer is A. Procurement type. In the material master, the Procurement Type (A) setting determines whether a material will be procured externally, produced in-house, or both. This setting is crucial for Material Requirements Planning (MRP), as it guides the MRP system on how to replenish the material - by…

Manufacturing

Question

When running MRP, what setting in the material master determines if a material will be procured or produced?

Options

  • AProcurement type
  • BPurchasing group
  • CMRP type
  • DProcessing key

How the community answered

(45 responses)
  • A
    91% (41)
  • B
    4% (2)
  • C
    2% (1)
  • D
    2% (1)

Explanation

In the material master, the Procurement Type (A) setting determines whether a material will be procured externally, produced in-house, or both. This setting is crucial for Material Requirements Planning (MRP), as it guides the MRP system on how to replenish the material - by generating purchase requisitions for external procurement or planned orders for in-house production.

Topics

#MRP#procurement type#material master#production planning