C_TS410_2504 · Question #16
When running MRP, what setting in the material master determines if a material will be procured or produced?
The correct answer is A. Procurement type. In the material master, the Procurement Type (A) setting determines whether a material will be procured externally, produced in-house, or both. This setting is crucial for Material Requirements Planning (MRP), as it guides the MRP system on how to replenish the material - by…
Question
When running MRP, what setting in the material master determines if a material will be procured or produced?
Options
- AProcurement type
- BPurchasing group
- CMRP type
- DProcessing key
How the community answered
(45 responses)- A91% (41)
- B4% (2)
- C2% (1)
- D2% (1)
Explanation
In the material master, the Procurement Type (A) setting determines whether a material will be procured externally, produced in-house, or both. This setting is crucial for Material Requirements Planning (MRP), as it guides the MRP system on how to replenish the material - by generating purchase requisitions for external procurement or planned orders for in-house production.