C_TPLM30_67 · Question #185

Your customer wants to assign maintenance orders to network activities automatically with the Maintenance Event Builder (MEB). Which of the following steps must you perform? (Choose two.)

The correct answer is C. Assign a network to a revision with revision type WPS-controlled. E. Assign the Reference PM/PS element to task list headers andnetwork activities. See the full explanation below for the reasoning.

Question

Your customer wants to assign maintenance orders to network activities automatically with the Maintenance Event Builder (MEB). Which of the following steps must you perform? (Choose two.)

Options

  • ASet the Define Transfer of Project or Invest Programindicator.
  • BAssign maintenance orders manually to a revision withrevision type WPS-controlled.
  • CAssign a network to a revision with revision type WPS-controlled.
  • DAssign a hierarchical task list to a notification.
  • EAssign the Reference PM/PS element to task list headers andnetwork activities.

How the community answered

(19 responses)
  • A
    11% (2)
  • B
    5% (1)
  • C
    79% (15)
  • D
    5% (1)