SAP
C_TPLM30_67 · Question #184
Your customer wants to generate costing for internal activities. For which of the following can you define various rates in Activity Type/Price Planning transaction? There are 3 correct answers to…
The correct answer is A. Plan/actual version B. Cost center C. Period. See the full explanation below for the reasoning.
Question
Your customer wants to generate costing for internal activities. For which of the following can you define various rates in Activity Type/Price Planning transaction? There are 3 correct answers to this question. Response:
Options
- APlan/actual version
- BCost center
- CPeriod
- DValue category
- EPlant
How the community answered
(23 responses)- A70% (16)
- D13% (3)
- E17% (4)
Community Discussion
No community discussion yet for this question.