C_TPLM30_67 · Question #184

Your customer wants to generate costing for internal activities. For which of the following can you define various rates in Activity Type/Price Planning transaction? There are 3 correct answers to…

The correct answer is A. Plan/actual version B. Cost center C. Period. See the full explanation below for the reasoning.

Question

Your customer wants to generate costing for internal activities. For which of the following can you define various rates in Activity Type/Price Planning transaction? There are 3 correct answers to this question. Response:

Options

  • APlan/actual version
  • BCost center
  • CPeriod
  • DValue category
  • EPlant

How the community answered

(23 responses)
  • A
    70% (16)
  • D
    13% (3)
  • E
    17% (4)

Community Discussion

No community discussion yet for this question.