Which of the following steps are required to create a measuring point for performance-based preventive maintenance? There are 2 correct answers to this question. Response:

The correct answer is A. Specify the annual estimated usage for the measuring point. D. Create the measuring point as a counter. See the full explanation below for the reasoning.

Question

Which of the following steps are required to create a measuring point for performance-based preventive maintenance? There are 2 correct answers to this question. Response:

Options

  • ASpecify the annual estimated usage for the measuring point.
  • BActivate the Measurement Reading Transfer indicator.
  • CDefine a valuation code group.
  • DCreate the measuring point as a counter.

How the community answered

(40 responses)
  • A
    83% (33)
  • B
    8% (3)
  • C
    10% (4)