Question

A user has planned an operation with labor costs and material costs; however, the material cost element is not assigned to a value category. Where do the material costs appear in the value categories for the order? Please choose the correct answer. Response:

Options

  • AIn the overhead value category
  • BIn a new, automatically created value category
  • CIn the unassigned value category
  • DIn the internal activity value category

How the community answered

(50 responses)
  • A
    16% (8)
  • B
    4% (2)
  • C
    72% (36)
  • D
    8% (4)