C_TPLM30_65 · Question #9
Your customer plans a plant shutdown and wants to use the Maintenance Event Builder to plan revisions and create maintenance orders automatically. What must you do in Customizing?
The correct answer is C. Create a revision type and select WPS-Controlled. See the full explanation below for the reasoning.
Question
Your customer plans a plant shutdown and wants to use the Maintenance Event Builder to plan revisions and create maintenance orders automatically. What must you do in Customizing?
Options
- ADefine field values for PM/PS Reference Element
- BDefine transfer of project or investment program
- CCreate a revision type and select WPS-Controlled.
- DCreate a revision type and select Not WPS-Controlled.
How the community answered
(26 responses)- A8% (2)
- B4% (1)
- C73% (19)
- D15% (4)