When the user creates a maintenance plan for a call object (order), which value in the planning data determines the order type?

The correct answer is C. Maintenance planner group. See the full explanation below for the reasoning.

Question

When the user creates a maintenance plan for a call object (order), which value in the planning data determines the order type?

Options

  • APriority
  • BMaintenance activity type
  • CMaintenance planner group
  • DMain work center

How the community answered

(33 responses)
  • A
    3% (1)
  • B
    9% (3)
  • C
    85% (28)