Which of the following combinations must you use to create a single-cycle maintenance plan for an external service?
The correct answer is B. A framework order and a maintenance order for settlement. See the full explanation below for the reasoning.
Question
Which of the following combinations must you use to create a single-cycle maintenance plan for an external service?
Options
- AA maintenance order for settlement and an outline agreement
- BA framework order and a maintenance order for settlement
- CA framework order and a subcontract purchase order
- DA subcontract purchase order and an outline agreement
How the community answered
(48 responses)- A4% (2)
- B83% (40)
- C8% (4)
- D4% (2)