C_TPLM30_65 · Question #32

C_TPLM30_65 Question #32: Real Exam Question with Answer & Explanation

Sign in or unlock C_TPLM30_65 to reveal the answer and full explanation for question #32. The question stem and answer options stay visible for context.

Question

What are the prerequisites for the calculation of planned costs in an order? (Choose three)

Options

  • AThe order operations must have a control key with the Costing indicator set in Customizing.
  • BThe user must save the order or execute the Determine costs function.
  • CThe cost elements must be assigned to the order type in Customizing.
  • DA costing variant for planned costs must be assigned to the order type in Customizing for order types.
  • EThe costing indicator must be set in Customizing for order types.

Unlock C_TPLM30_65 to see the answer