Which scheduling parameter adjusts the cycle intervals of a maintenance strategy for each maintenance plan?
The correct answer is D. The cycle modification factor. See the full explanation below for the reasoning.
Question
Which scheduling parameter adjusts the cycle intervals of a maintenance strategy for each maintenance plan?
Options
- AThe call horizon
- BThe early and late shift factors
- CThe early and late tolerance
- DThe cycle modification factor
How the community answered
(31 responses)- A16% (5)
- B10% (3)
- C3% (1)
- D71% (22)
Community Discussion