C_TPLM22_67 · Question #170
Which of the following rules do you use to specify the proportion of costs that should be settled to receivers while maintaining settlement rule for WBS element or networks and activities in an…
The correct answer is D. Distribution rules. See the full explanation below for the reasoning.
Question
Which of the following rules do you use to specify the proportion of costs that should be settled to receivers while maintaining settlement rule for WBS element or networks and activities in an overview screen? Please choose the correct answer. Response:
Options
- AProportion rules
- BProject rules
- CSettlement rules
- DDistribution rules
How the community answered
(48 responses)- A15% (7)
- B8% (4)
- C4% (2)
- D73% (35)
Community Discussion